00:00-00:45 | Project selection
ACTION: Open Projects & Tenders. Select FX-TDR-2611-003, the fictional Pipe Rack Structural Module M-03.
SAY: FABRIX complements Tekla; it is not a Tekla replacement. Today we use a fictional pipe-rack project, with independent synthetic reference files for each engineering input path.
EXPECTED: The selected pipe-rack project is a DEMO record, not a confidential real project.

00:45-01:35 | Import IFC4 geometry
ACTION: Open Model Intelligence > Import IFC model. Select 01_IFC4_Mini_Frame.ifc and examine the viewer and quantity summary.
SAY: The IFC mini-frame contains three model elements, with quantities declared for two. The third object has no weight or volume and is held back rather than assigned a fictional quantity.
EXPECTED: 3 elements; 2 with quantities; 1 held back; about 0.424 tonnes from the IFC.

01:35-02:15 | Apply reviewed quantities
ACTION: In the IFC import review click Add 2 and update 0 row(s). Confirm the active project has nine parts.
SAY: This is the difference between previewing IFC information and accepting two quantity rows into the project. The demonstration part register grows from seven to nine rows.
EXPECTED: 7 existing rows -> 9 after IFC import. IFC mesh geometry was not used as a weight estimate.

02:15-03:05 | Import Tekla-style connection data
ACTION: Open Connection Library > Register & groups and import 02_Tekla_Connections_Revision_A.json.
SAY: The reference JSON supplies thirty-three weld rows, resolved into eleven distinct physical connections. Multiple weld records can refer to one physical joint.
EXPECTED: 33 weld rows -> 11 physical connections; no live licensed Tekla workstation was used.

03:05-03:55 | Select ten identical joints
ACTION: Choose the IPE300/PL10 group whose register count is ten. Inspect weld type, process, member and plate information.
SAY: Connection fingerprinting allows one calculation to be reused for truly identical fabrication scope. Different preparation or details must produce a separate calculation.
EXPECTED: One calculation target covers ten repeated physical connections.

03:55-04:50 | Calculate and record a local check
ACTION: Click Calculate / reuse, enter Demonstration Checker and choose Record local check.
SAY: The calculation groups fabrication work into traceable hours and costs. This local check records sample verification and is not an authenticated company engineering approval.
EXPECTED: Baseline 16.04 fabrication labour hours, 4.14 machine hours separately, AED 991 fictional cost.

04:50-05:45 | Add recorded scaffold allowance
ACTION: Engineering Workspace > Access & scaffolding. Enter 3.5 m, scaffold, required Yes, setup 2 h, access 0.7 h per joint, rate 60 AED/h, plus synthetic evidence.
SAY: Setup is counted only once. Two hours plus zero point seven hours for each of ten connections equals nine added labour hours. The example rate produces five hundred forty dirhams of extra cost.
EXPECTED: 2 + (10 x 0.7) = 9.00 h, and 9 x AED 60 = AED 540.

05:45-06:45 | Issue local card and export files
ACTION: Connection Library > Calculations > Issue job card. Confirm in Job cards, then download PDF, Excel and CSV.
SAY: The locally checked card preserves the fabrication baseline and prints access as a separate additive line. Fabrication labour sixteen point zero four plus nine access equals twenty-five point zero four hours. Machine hours are separate, not additional labour.
EXPECTED: Total 25.04 labour hours, 4.14 machine hours; cost AED 991 + 540 = AED 1,531.

06:45-07:40 | Apply Tekla Revision B
ACTION: Import 03_Tekla_Connections_Revision_B.json, then apply model revision and reissue from Job cards.
SAY: One changed joint splits the matching configuration. The original locally checked Rev 1 is superseded, while the new Rev 2 remains a draft until verified.
EXPECTED: Nine matching in revised group; Rev 1 superseded; Rev 2 draft.

07:40-08:35 | Deck fabrication data
ACTION: Deck Job Cards > Import master table: 04_Fabrication_Master_Table.csv. Then Import part list: 05_Fabrication_Part_List.csv.
SAY: This is a separate fabrication-workbook workflow. The actual imported fixture has seven thousand nine hundred fifty-nine master weld rows, one thousand four hundred twenty-one parts and eight decks.
EXPECTED: 7,959 weld rows; 1,421 parts; 8 decks. No automatic IFC-to-weld-master conversion claimed.

08:35-09:20 | Export deck work packages
ACTION: Use the Deck Job Cards Excel workbook button, open the downloaded workbook and inspect one deck.
SAY: The sample calculates twenty-one thousand planned hours across eight decks. Some weights and lifting counts are missing, and a simple triangular groove-weld approximation remains flagged for engineering checking.
EXPECTED: 21,000 planned hours; missing deck weight prevents meaningful man-hours per tonne.

09:20-10:00 | Close and answer questions
ACTION: Show the real downloaded PDF, Excel and CSV; finish with the acceptance limitations.
SAY: These are verified synthetic demonstrations of the software workflow, not approved structural calculations. Before company issue, validate against licensed Tekla, released drawings and WPS, engineering time studies and approved commercial rates.
EXPECTED: Demo workflow passes; formal shop release and actual Tekla verification remain pending.